Quaterra Releases Favourable Preliminary Economic Asssessment on Nieves Silver Project Showing Potential for Open Pit Silver Mine Producing More Than Five Million Ounces a Year

10,000 tonne-per-day project would produce 55.5 million ounces of silver over 10-year mine life


VANCOUVER, BRITISH COLUMBIA--(Marketwire - Sept. 19, 2012) - Quaterra Resources Inc. (TSX VENTURE:QTA)(NYSE MKT:QMM)(NYSE Amex:QMM) and its 50% joint-venture partner Blackberry Ventures I, LLC, today announced that an independent preliminary economic assessment has concluded that their Nieves silver property in Zacatecas State, Mexico, has the potential to be developed as an open pit mine that would average more than five million ounces of silver production per year over a projected ten-year mine life.

The preliminary economic assessment (PEA), undertaken by M3 Engineering & Technology Corp. (M3) of Tucson, Arizona, sets out the following key project parameters:

  • An open pit centered on the Concordia vein that contains a total of 35.4 million tonnes. The pit is based on an indicated resource of 33.0 million tonnes at 50.1g/t silver and an inferred resource of 39.3 million tonnes at 32.0 g/t silver, using a cutoff of 15 grams.
  • Recovery of 55.5 million ounces of silver and 41,000 ounces of gold over the 10-year mine life at an average mining rate of 3.5 million tonnes per year. Silver recoveries of 86% were based on testwork completed to date.
  • Initial capital expenditure of US$231.6 million (U.S. dollars are used in this press release unless otherwise stated).
  • Average life-of-mine operating costs of $14.98 per ounce of payable silver.
  • An after tax net present value (NPV) of $77.1 million at an 8% discount rate and a base case silver price of $27 per ounce. The before tax NPV is $142.32 million. At a silver price of $32.40 the after tax NPV is $204 million. The project breaks even at a silver price of about $21.37 per ounce (about $15.25 after payback).
  • An after tax internal rate of return (IRR) of 15.7% with a 4.4-year pay back. The before tax IRR is 21.9% with a 3.4-year pay back.

"The PEA confirms our expectation that Nieves is an attractive open pit silver project based on a conservative silver price," says Quaterra President and CEO Thomas Patton. "And it is highly leveraged to any upward movement in the silver price, with an after tax increase in net present value of about $23 million for every one dollar increase in silver above the base case. Also, exploration and drilling provide good potential not only to expand the current pit but also to upgrade the San Gregorio inferred resource which was not included in this study."

The San Gregorio inferred resource includes 16.3 million ounces of silver and 48,300 ounces of gold using a cutoff of 15 grams. In addition, one drill rig is currently on site testing gold-silver anomalies on the West Santa Rita vein and several other high-priority geophysical anomalies.

The Nieves project is located within the Mexican silver belt in Zacatecas State, Mexico, in a mining-friendly area of flat vacant land with excellent infrastructure including power and water. In June this year, Quaterra released a NI43-101-compliant resource estimate for mineralization associated with the Concordia and San Gregorio vein systems. (Please see news release of June 27, 2012).

Updated Mineral Resource

The PEA is based on an indicated resource of 33.0 million tonnes at 50.1 g/t silver and an inferred resource of 39.3 million tonnes at 32.0 g/t silver, using a cutoff of 15 grams. The NI43-101-compliant resource was completed by Caracle Creek International Consulting Inc. of Toronto, Canada, in June 2012.

TABLE 1
NIEVES SILVER PROJECT - CONCORDIA AND SAN GREGORIO VEIN SYSTEMS
ESTIMATED MINERAL RESOURCES, JUNE 20121
Vein Zone Classification Tonnes
(t)
2
Ag
(g/t)
Au
(g/t)
Ag
(oz)
3
Au
(oz)
3
Concordia La Quinta Indicated 33,038,000 50.1 0.04 53,216,700 42,500
Concordia La Quinta Inferred 39,258,000 32.0 0.02 40,390,300 25,200
San Gregorio North Inferred 18,769,000 27.0 0.08 16,292,800 48,300
  1. Prepared by Jason Baker, P.Geo., Geological Engineer, Caracle Creek International Consulting Inc., an independent Qualified Person within the meaning of NI43-101, using a reporting cut-off grade of 15 g/t Ag. Au is reported to 2 decimal places and Ag to 1 decimal place.
  2. Tonnes rounded to the nearest 1,000.
  3. 1 troy ounce = 31.103 grams.

Mine Plan

The Nieves open pit straddles the Concordia vein and includes three pit phases. A 35.4-million tonne mineralized zone would be mined at a rate of 10,000 tonnes per day resulting in a ten year mine life and at a 5.4:1 (waste to ore) strip ratio. The pit includes 28.3 million tonnes of higher grade material averaging 65 g/t silver and 0.045 g/t gold (at a cutoff of 30.5 g/t silver); and 7.1 million tonnes of lower grade material averaging 24 g/t silver (at a cutoff of 21.3 g/t silver). The San Gregorio zone was not included in the mine plan but may become viable with additional drilling.

The pit will be mined primarily using two 16.5-cubic meter hydraulic shovels loading 90-tonne haul trucks. A 12-cubic meter front end loader will be used as backup to the shovels and two diesel powered rotary drills will be used for production. The major support equipment will include three dozers, a grader, a pre-shear drill and a water truck.

Capital Costs

Initial capital costs and sustaining capital costs are shown in the table below. Capital costs are considered accurate to +/- 35%.

TABLE 2
NIEVES SILVER PROJECT- ZACATECAS, MEXICO
INITIAL AND SUSTAINING CAPITAL
Sep-12
INITIAL CAPITAL SUSTAINING CAPITAL
Mine/equipment 44,407,000 31,085,000
Process Plant1 169,920,000 33,000,000
Owners Cost2 17,325,000
TOTAL 231,652,000 64,085,000
  1. Includes infrastructure costs. 2. Includes management, overhead and G&A.

Operating costs

Ore will be processed using primary crushing followed by grinding in a SAG/ball mill circuit. Ore will then be treated using conventional rougher/cleaner flotation. Following flotation, concentrate will be filtered and bagged for shipment and smelting within Mexico. A conventional tailing facility is planned at a location downgradient of the mineral processing site. Project infrastructure includes maintenance, warehousing, shop facilities, access roads, grid power and water wells.

TABLE 3
NIEVES SILVER PROJECT- ZACATECAS, MEXICO
OPERATING COSTS
Sep-12
COST/OZ
PAYABLE AG
COST/TONNE
ORE
Mine 4.56 $6.75
Concentrator 6.37 $9.43
G & A 0.95 $1.41
TC/RC1 3.1 $4.59
TOTAL 14.98 $22.18

1. Treatment and refining charges.

Financial Analysis

The financial analysis is based on a silver price of $27 per ounce and a gold price of $1,300 per ounce, rounded numbers which are both less than the SEC-recommended three-year historical price through the end of August. The analysis includes deductions for all royalty payments and a contingency of 20%. No credits are assumed for lead or zinc.

The after and before tax NPV, internal rate of return and payback period for the base case is summarized below:

TABLE 4
NIEVES SILVER PROJECT- ZACATECAS, MEXICO
ECONOMIC INDICATORS
Sep-12
BEFORE TAX AFTER TAX
NPV @ 8%, $ 142,319,000 77,116,000
IRR, % 21.9 15.7
Pay Back, years 3.4 4.4

Sensitivities were run for the price of silver, operating cost and initial capital cost. Table 5 below summarizes the NPV, IRR and pay-back with variances of +/- 20%.

TABLE 5
NIEVES SILVER PROJECT- ZACATECAS, MEXICO
SENSITIVITY TABLE
Sep-12
Silver Price $/oz Ag After Tax
NPV @ 8%
IRR
(%)
Payback
(yrs)
Base 27.00 77,116,000 15.7 4.4
plus 20% 32.40 204,393,000 26.6 3.1
minus 20% 21.60 -59,076,000 1.1 9.9
Operating Cost $/oz
payable
Ag
After Tax
NPV @ 8%
IRR
(%)
Payback
(yrs)
Base 14.98 77,116,000 15.7 4.4
plus 20% 17.91 1,017,000 8.1 5.7
minus 20% 12.04 148,637,000 22 3.6
Initial Capital ($) After Tax
NPV @ 8%
IRR
(%)
Payback
(yrs)
Base 231,652,000 77,116,000 15.7 4.4
plus 20% 277,982,000 40,973,000 11.6 5.2
minus 20% 185,322,000 112,612,000 21.3 3.6

A PEA should not be considered to be a pre-feasibility or feasibility study, as the economics and technical viability of the project have not been demonstrated at this time. It is preliminary in nature and includes inferred mineral resources that are considered too geologically speculative at this time to have economic considerations applied to them to be categorized as mineral reserves. Thus, there is no certainty that the production profile concluded in the PEA will be realized. Actual results may vary, perhaps materially.

Thomas Patton is the Qualified Person with Quaterra responsible for this news release. The Qualified Person for the updated Nieves project resource estimate in this release is Jason Baker, P. Geo, of Caracle Creek International Consulting Inc. of Toronto, Canada. The Qualified Person for the preliminary economic assessment portion of this release is Joshua Snider P.E. with M3 Engineering & Technology Corp., Tucson, Arizona. The Qualified Person for the mining portion of this release is Jeffery Choquette P.E. of Butte, Montana, and for metallurgy Thomas L. Drielick P.E. M3 Engineering & Technology Corp., Tucson, Arizona.

The NI43-101-compliant Technical Report for the Nieves PEA, including a description of the project resources, mine plan, metallurgy, capital costs, operating costs and financial analysis, will be filed within 45 days of the date of this release. This report will be available at www.sedar.com.

Quaterra Resources Inc. (TSX VENTURE:QTA)(NYSE MKT:QMM)(NYSE Amex:QMM) is a junior exploration company focused on making significant mineral discoveries in North America. The Company uses in-house expertise and its network of consultants, prospectors and industry contacts to identify, acquire and evaluate prospects in mining-friendly jurisdictions with the potential to host large and/or high-grade base and precious metal deposits.

On behalf of the Board of Directors,

Dr. Thomas Patton, President and CEO, Quaterra Resources Inc.

Disclosure note

The results of the Nieves resource estimate have been reviewed by Quaterra technical staff. The Company believes that the Nieves resource estimate was conducted in a professional and competent manner. Inferred resources are resources that have not been defined in sufficient detail to be characterized as Measured or Indicated resources. Mineral resources have not had economic considerations applied to them and are therefore not characterized as Reserves.

The mining terms "indicated resource" and "inferred resource" are used in this news release in accordance with Canadian regulations but are not recognized by the United States Securities and Exchange Commission. For clarification, the Company has no properties that contain "reserves" as defined by the SEC and is providing the forgoing, in part, in order to meet its requirements under National Instrument 43-101 adopted by the BC Securities Commission and the Canadian Securities Administrators.

A PEA should not be considered to be a pre-feasibility or feasibility study, as the economics and technical viability of the Project has not been demonstrated at this time. A PEA is preliminary in nature and includes Inferred mineral resources that are considered too geologically speculative at this time to have the economic considerations applied to them to be categorized as mineral reserves. Thus, there is no certainty that the production profile concluded in the PEA will be realized. Actual results may vary, perhaps materially.

Some statements contained in this news release are forward-looking statements within the safe harbor of the Private Securities Litigation Reform Act of 1995. These statements generally are identified by words such as the Company "believes", "expects", and similar language, or convey estimates and statements that describe the Company's future plans, objectives or goals. Since forward-looking statements are based on assumptions and address future events and conditions, by their very nature they involve inherent risks and uncertainties. Further information regarding risks and uncertainties which may cause results to differ materially from those projected in forward-looking statements, are included in filings by the Company with securities regulatory authorities. Readers are cautioned not to place undue reliance on forward-looking statements, which speak only as of the date thereof. The Company does not undertake to update any forward-looking statement that may be made from time to time except in accordance with applicable securities laws. References may be made in this press release to historic mineral resource estimates. None of these are NI 43-101 compliant and a qualified person has not done sufficient work to classify these historic estimates as a current mineral resource. They should not be relied upon and Quaterra does not treat them as current mineral resources.

Expanded information on the Company's projects is described on our website at www.quaterra.com.

Should you wish to receive news releases by fax please contact Quaterra Resources Inc. at 604-681-9059 (direct), 1-855-681-9059 (toll free) or email info@quaterra.com.

The TSX Venture Exchange and the American Stock Exchange have not reviewed and do not accept responsibility for the adequacy or accuracy of the contents of this news release, which has been prepared by management.

Contact Information:

Quaterra Resources Inc.
Thomas Patton
President and CEO
604-641-2758

Quaterra Resources Inc.
Lauren Stope
Manager Communications
604-641-2746
info@quaterra.com
www.quaterra.com